IFUGAO Project Sites

updatedas of December 29, 2016

***Hover mouse over project icons to see details of Sub-projects***

LEGEND
FMR Farm-to-Market Road(FMR)
Foot Bridge Foot Bridge(FB)
Domestic Water Supply Domestic Water Supply(DWS)
Communal Irrigation System Communal Irrigation System(CIS)
Foot Path Foot Path/Trail(FP/FT)
Home Community Infrastructure-MP Warehouse/MPDP
Refo/ANR Reforestation/ANR & Agroforestry
Physically Completed Sub-Projects Physically Completed Sub-Projects
Cancelled Sub-Projects Cancelled Sub-Projects

 

FMR Proponent :MLGU
Province :IFUGAO
Municipality:MAYOYAO
Barangay :MAGULON
Name of Sub-Project:Improvement of BULHE-MAGULON FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status: COMPLETED
CFA/Non-CFA:CFA (75M)
Quantity:3.1
Unit:KMS.
Total Project Cost:4,000,000.00
Fund Source:OFID
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED, 100% PROJECT COUNTERPART RELEASED
FMR (1)Proponent:MLGU
Province :IFUGAO
Municipality:TINOC
Barangay :AHIN
Name of Sub-Project:Improvement/Rehab. of TULUDAN-AHIN FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status:COMLETED
CFA/Non-CFA:NON-CFA
Quantity:4.4
Unit:KMS.
Total Project Cost:7,100,000.00
Fund Source:IFAD
% Physical Accomplishment:100%
REMARKS: PHYSICALLY COMPLETED, 100% PROJECT COUNTERPART RELEASED

(2)Proponent:MLGU
Province :IFUGAO
Municipality:TINOC
Barangay : AHIN
Name of Sub-Project:Improvement/Rehab. of TULUDAN-AHIN FMR Ph.2
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status: COMPLETED
CFA/Non-CFA:NON-CFA
Quantity:0.78
Unit:KMS.
Total Project Cost:2,000,000.00
Fund Source:IFAD
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED
FMR Proponent :PLGU
Province :IFUGAO
Municipality:HINGYON
Barangay :MOMPOLIA
Name of Sub-Project:Improvement/Rehabilitation of IBALIW-BANE FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status: COMPLETED
CFA/Non-CFA:CFA (50M)
Quantity:2.0
Unit:KMS.
Total Project Cost:4,010,471.07
Fund Source:OFID
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED, 100% PROJECT COUNTERPART RELEASED
Ifugao Map
FMR Proponent :MLGU
Province :IFUGAO
Municipality:MAYOYAO
Barangay :CHAYA
Name of Sub-Project:Improvement/Rehab. of CHAYA FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status:COMPLETED
CFA/Non-CFA:CFA (50M)
Quantity:1.71
Unit:KMS.
Total Project Cost:3,400,000.00
Fund Source:OFID
% Physical Accomplishment:100%
REMARKS:PHYSICALLY COMPLETED,100% PROJECT COUNTERPART RELEASED
FMR Proponent :MLGU
Province :IFUGAO
Municipality:MAYOYAO
Barangay :CHUMANG
Name of Sub-Project:Improvement/Rehab. of CHUMANG FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status:COMPLETED
CFA/Non-CFA:CFA (50M)
Quantity:1.51
Unit:KMs.
Total Project Cost:3,020,000.00
Fund Source:OFID
% Physical Accomplishment:100%
REMARKS:PHYSICALLY COMPLETED,100% PROJECT COUNTERPART RELEASED

 

FMR Proponent :MLGU
Province :IFUGAO
Municipality:MAYOYAO
Barangay :NATUM
Name of Sub-Project:Rehabilitation of NALBU-ALIMIT-NATUM FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status: COMPLETED
CFA/Non-CFA:CFA (75M)
Quantity:10.05
Unit:KMS.
Total Project Cost:4,000,000.00
Fund Source:OFID
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED,100% PROJECT COUNTERPART RELEASED

 

 

 

 

 

 

 

Tree Type of Project : Agroforestry
Name of People's Org'n : Namal Farmers Association
Location : Namal, Asipulo, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 10.00 Has.
Total Cost : 320,000.00
Agro Plots : 15
Area Planted(Ha.) : 10.00 Has.
Area Planted(%) : 100%
Species Planted : Coffee
Total Amt. Released : 271,652.77
Balance Amount : 48,347.23
REMARKS : Activities completed

 

Communal Irrigation System (1)Proponent:MLGU
Province :IFUGAO
Municipality:HUNGDUAN
Barangay :MAGGOK
Name of Sub-Project:Rehabilitation of MUMBUNGOG CIS
Sub-Project Type:COMMUNAL IRRIGATION SYSTEM
Implementation Status: COMPLETED
CFA/Non-CFA:NON CFA
Quantity:16
Unit:HAS.
Total Project Cost:2,000,000.00
Fund Source:OFID
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED,100% PROJECT COUNTERPART RELEASED

(2)Proponent:MLGU
Province :IFUGAO
Municipality:HUNGDUAN
Barangay :MAGGOK
Name of Sub-Project:Rehabilitation of MUMBUNGOG CIS Ph. 2
Sub-Project Type:COMMUNAL IRRIGATION SYSTEM
Implementation Status: ON-GOING
CFA/Non-CFA:NON CFA
Quantity:8
Unit:HAS.
Total Project Cost:1,000,000.00
Fund Source:IFAD
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED

 

 

FMR Proponent :MLGU
Province :IFUGAO
Municipality:HUNGDUAN
Barangay :BANGBANG
Name of Sub-Project:BANGBANG FMR Improvement Project
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status: COMPLETED
CFA/Non-CFA: NON-CFA
Quantity:4.80
Unit:KMS.
Total Project Cost:4,200,000.00
Fund Source:IFAD
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED

 

FMR Proponent :MLGU
Province :IFUGAO
Municipality:HUNGDUAN
Barangay :LUBO-ONG
Name of Sub-Project:BAGTUNA-MT. POLIS Road Improvement
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status: COMPLETED
CFA/Non-CFA: NON-CFA
Quantity:14
Unit:KMS.
Total Project Cost:4,200,000.00
Fund Source:IFAD
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED

 

 

 

 

 

Summary: OVERALL PHYSICAL STATUS of Infra sub-projects(IFUGAO)

Total no. of Sub-Projects(SPs): 23

Physically Completed SPs: 22(96% Overall)

Status of On-going Sub-Projects: 1 sub-project on-going/for completion

Municipality Barangay Name of Sub-Project Sub-project Type %Physical Accomplishment REMARKS
Tinoc Danggo DANGGO IP Hall COMMUNITY INFRASTRUCTURE 50% On-going Implementation

COMPONENT UPDATES:pdf iconDetailed/Tabular Format

  • Equipment
  • ESF Training
  • FBS
  • Financial Literacy
  • LAF
  • Learning Visits
  • O and M Training
  • Production Training
  • Skills Training
  • Starter Kits(Meat/Food)
  • Supplies/Materials
  • Techno Demo

 

Tree (1)Type of Project : Reforestation
Location : Tukucan, Tinoc, IFUGAO
Name of People's Org'n : Tukucan Farmers Organization, Inc.
Name of PO/IPO Pres. : Louis A. Calabson
Project Cost : 780,860.00
Total Area : 35 Has.
Date Started : February 28,2013
Date Completion(Revised): June 2016
No. of refo sites : 1
Area Planted/% Planted : 35 Has./100%
Total Amount Released : 379,854.00
Balance Amount : 401,006.00
REMARKS : Last pass maintenance not yet conducted

(2)Type of Project : Agroforestry
Name of People's Org'n : Tukucan Farmers Organization, Inc.
Location : Tukucan, Tinoc, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 16.67 Has.
Total Cost : 533,440.00
Date Started : October 2014
Date Completion(Revised): October 2015
Agro Plots : 24
Area Planted(Ha.) : 16.67 Has.
Area Planted(%) : 100%
Species Planted : Coffee
Total Amt. Released : 415,840.16
Balance Amount : 117,599.84
REMARKS : Activities completed
Tree (1)Type of Project : Reforestation
Location : Luhong, Tinoc, IFUGAO
Name of People's Org'n : Luhong Farmers Organization
Name of PO/IPO Pres. : Jose D. Tayaban
Project Cost : 2,088,000.00
Total Area : 90 Has.
Date Started : February 28,2013
Date Completion(Revised): June 2016
No. of refo sites : 3
Area Planted/% Planted : 90 Has./100%
Total Amount Released : 1,432,080.00
Balance Amount : 655,920.00
REMARKS : Last pass maintenance not yet conducted

(2)Type of Project : Agroforestry
Name of People's Org'n : Luhong Farmers' Organization Location : Luhong, Tinoc, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 11.2 Has.
Total Cost : 358,400.00
Date Started : October 2014
Date Completion(Revised): October 2015
Agro Plots : 28
Area Planted(Ha.) : 11.2 Has.
Area Planted(%) : 100%
Species Planted : Coffee and Citrus
Total Amt. Released : 286.365.14
Balance Amount : 72,034.86
REMARKS : Activities completed
Tree (1)Type of Project : Reforestation
Location : Danggo, Tinoc, IFUGAO
Name of People's Org'n : Danggo Farmers Organization
Name of PO/IPO Pres. : Reymundo I. Berting
Project Cost : 464,000.00
Total Area : 20 Has.
Date Started : February 28,2013
Date Completion(Revised): March 2016
No. of refo sites : 1
Area Planted/% Planted : 20 Has./100%
Total Amount Released : 338,940.00
Balance Amount : 125,060.00
REMARKS : Last pass maintenance not yet conducted

(2)Type of Project : Agroforestry
Name of People's Org'n : Danggo Farmer's Organization
Location : Danggo, Tinoc, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 11 Has.
Total Cost : 352,000.00
Agro Plots : 25
Area Planted(Ha.) : 6.66 Has.
Area Planted(%) : 60.54%
Species Planted : Coffee and Citrus
Total Amt. Released : -
Balance Amount : -
Physical Status : Procurement of seedlings on-going
Tree (1)Type of Project : Reforestation
Location : Ahin, Tinoc, IFUGAO
Name of People's Org'n : Ahin Farmers Development Organization, Inc.
Name of PO/IPO Pres. : Glory Santiban
Project Cost : 1,196,020.00
Total Area : 52 Has.
Date Started : May 5,2013
Date Completion(Revised): March 2016
No. of refo sites : 3
Area Planted/% Planted : 52 Has./100%
Total Amount Released : 671,111.92
Balance Amount : 524,908.08
REMARKS : Last pass maintenance not yet conducted

(2)Type of Project : Agroforestry
Name of People's Org'n : Ahin Farmers Development Association, Inc. Location : Ahin, Tinoc, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 10 Has.
Total Cost : 320,000.00
Date Started : October 2014
Date Completion(Revised): October 2015
Agro Plots : 25
Area Planted(Ha.) : 10 Has.
Area Planted(%) : 100%
Species Planted : Coffee and Citrus
Total Amt. Released : 255,457.84
Balance Amount : 64,542.16
REMARKS : Activities completed
Tree (1)Type of Project : Reforestation
Location : Maggok, Hungduan, IFUGAO
Name of People's Org'n : Maggok Indigent Helpful & Responsible Parent Organization
Name of PO/IPO Pres. : Edwin T. Dulnuan
Project Cost : 1,531,200.00
Total Area : 66(36 Refo/30 Expansion)Has.
Date Started : February 28,2013/April 2014(Expansion)
Date Completion(Revised): December 2015/December 2015
No. of refo sites : 3
Area Planted/% Planted : 66 Has./100%
Total Amount Released : 1,203,993.00
Balance Amount : 327,207.00
REMARKS : Activities completed/Last pass maintenance not yet conducted(Expansion)

(2)Type of Project : Agroforestry
Name of People's Org'n : Maggok farmers and Irrigators Association
Location : Maggok, Hungduan, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 18.62 Has.
Total Cost : 595,840.00
Date Started : October 2014
Date Completion(Revised): March 2015
Agro Plots : 38
Area Planted(Ha.) : 18.62 Has.
Area Planted(%) : 100%
Species Planted : Coffee
Total Amt. Released : 536,256.00
Balance Amount : 59,584.00
REMARKS : Activities completed
Tree (1)Type of Project : Reforestation
Location : Cawayan, Asipulo, IFUGAO
Name of People's Org'n : Cawayan Farmers Association
Name of PO/IPO Pres. : Anacleto A. Tayaban
Project Cost : 1,160,000.00
Total Area : 50 Has.
Date Started : February 27,2012
Date Completion(Revised): December 2015
No. of refo sites : 4
Area Planted/% Planted : 50 Has./100%
Total Amount Released : 706,331.25
Balance Amount : 453,668.75
REMARKS : Activities completed

(2)Type of Project : Agroforestry
Name of People's Org'n : Cawayan Farmers Association
Location : Cawayan, Asipulo, IFUGAO
Name of PO/IPO Pres. : Anacleto A. Tayaban
Total Area : 7 Has.
Total Cost : 224,000.00
Date Started : February 8,2013
Date Completion(Revised): February 2015
Agro Plots : 15
Area Planted(Ha.) : 7 Has.
Area Planted(%) : 100%
Species Planted : Rambutan/Lanzones
Total Amt. Released : 201,600.00
Balance Amount : 22,400.00
REMARKS : Activities completed

(2)Type of Project : Agroforestry(Cawayan 2nd Batch)
Name of People's Org'n : Cawayan Farmers Association
Location : Cawayan, Asipulo, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 16 Has.
Total Cost : 512,000.00
Date Started : September 25,2014
Date Completion(Revised): January 2015
Agro Plots : 30
Area Planted(Ha.) : 16 Has.
Area Planted(%) : 100%
Species Planted : Rambutan/Lanzones
Total Amt. Released : -
Balance Amount : 421,600.00
REMARKS : Activities completed
Tree (1)Type of Project : Reforestation
Location : Ubuag, Hingyon, IFUGAO
Name of People's Org'n : Ubuag Farmers Organization
Name of PO/IPO Pres. : Jessie H. Habbiling
Project Cost : 2,987,260.00
Total Area : 148(65 Refo/83 Expansion)Has.
Date Started : February 27,2012/May 13,2014
Date Completion(Revised): March 2015/December 2015
No. of refo sites : 1
Area Planted/% Planted : 148 Has./100%
Total Amount Released : 2,278,984.50
Balance Amount : 708,275.50
REMARKS : Activities completed/last pass maintenance not yet conducted

(2)Type of Project : Agroforestry
Name of People's Org'n : Ubuag Farmers Organization
Location : Ubuag, Hingyon, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 15.00 Has.
Total Cost : 480,000.00
Date Started : February 13, 2014
Date Completion(Revised): September 2015
Agro Plots : 39
Area Planted(Ha.) : 15.00 Has.
Area Planted(%) : 100%
Species Planted : Rambutan
Total Amt. Released : 432,000.00
Balance Amount : 48,000.00
REMARKS : Activities completed
Tree (1)Type of Project : Reforestation
Location : Lubo-ong, Hungduan, IFUGAO
Name of People's Org'n : Lubu-ong Irrigators Association
Name of PO/IPO Pres. : -
Project Cost : 1,160,000.00
Total Area : 50 Has.
Date Started : February 27,2012
Date Completion(Revised): December 2014
No. of refo sites : 1
Area Planted/% Planted : 50 Has./100%
Total Amount Released : 1,044,000.00
Balance Amount : 116,000.00
REMARKS : Activities completed

(2)Type of Project : Agroforestry
Name of People's Org'n : Lubu-ong Bimmoble Organization
Location : Lubo-ong, Hungduan, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 8.82 Has.
Total Cost : 282,240.00
Date Started : October 2014
Date Completion(Revised): September 2015
Agro Plots : 34
Area Planted(Ha.) : 8.82 Has.
Area Planted(%) : 100%
Species Planted : Coffee
Total Amt. Released : 254,016.00
Balance Amount : 28,224.00
REMARKS : Activities completed
Tree (1)Type of Project : Reforestation
Location : Bangbang, Hungduan, IFUGAO
Name of People's Org'n : Bangbang Responsible Parents Organization
Name of PO/IPO Pres. : Imelda P. Biyong
Project Cost : 1,160,000.00
Total Area : 50 Has.
Date Started : February 27,2012
Date Completion(Revised): December 2014
No. of refo sites : 2
Area Planted/% Planted : 50 Has./100%
Total Amount Released : 1,043,962.50
Balance Amount : 116,037.50
REMARKS : Activities completed

(2)Type of Project : Agroforestry
Name of People's Org'n : Bangbang Farmers Irrigators Association
Location : Bangbang, Hungduan, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 10.87 Has.
Total Cost : 347,840.00
Agro Plots : 31
Date Started : October 2014
Date Completion(Revised): September 2015
Area Planted(Ha.) : 10.87 Has.
Area Planted(%) : 100%
Species Planted : Coffee
Total Amt. Released : 281,250.41
Balance Amount : 66,589.59
REMARKS : Activities completed
Tree (1)Type of Project : Reforestation
Location : Chumang, Mayoyao, IFUGAO
Name of People's Org'n : Chumang Upland & Livelihood Organization
Name of PO/IPO Pres. : Juan A. Boocan
Project Cost : 1,948,800.00
Total Area : 84(50 Refo/34 Expansion)Has.
Date Started : February 27,2012/February 15,2014(Expansion)
Date Completion(Revised): March 2015/March 2016(Expansion)
No. of refo sites : 2
Area Planted/% Planted : 84 Has./100%
Total Amount Released : 1,553,337.00
Balance Amount : 395,463.00
REMARKS : Activities completed/Last pass maintenance not yet conducted

(2)Type of Project : Agroforestry
Name of People's Org'n : Chumang Upland Farmers and Livelihood Organization
Location : Chumang, Mayoyao, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 9.51 Has.
Total Cost : 304,320.00
Date Started : October 2014
Date Completion(Revised): September 2015
Agro Plots : 31
Area Planted(Ha.) : 9.51 Has.
Area Planted(%) : 100%
Species Planted : Coffee
Total Amt. Released : 273,888.00
Balance Amount : 30,432.00
REMARKS : Activities completed
Tree (1)Type of Project : Reforestation
Location : Pula, Asipulo, IFUGAO
Name of People's Org'n : Pula Farmers Association
Name of PO/IPO Pres. : Christina Binnang
Project Cost : 1,160,000.00
Date Started : August 20,2012
Date Completion(Revised): December 2015
Total Area : 50 Has.
No. of refo sites : 2
Area Planted/% Planted : 50 Has./100%
Total Amount Released : 748,987.50
Balance Amount : 411,012.50
REMARKS : Activities completed

(2)Type of Project : Agroforestry
Name of People's Org'n : Pula Farmers Association
Location : Pula, Asipulo, IFUGAO
Name of PO/IPO Pres. : Christina Binnang
Total Area : 14.00 Has.
Total Cost : 448,000.00
Date Started : February 8,2013
Date Completion(Revised): October 2015
Agro Plots : 28
Area Planted(Ha.) : 14.00 Has.
Area Planted(%) : 100%
Species Planted : Rambutan/Lanzones
Total Amt. Released : 383,364.45
Balance Amount : 64,635.55
REMARKS : Activities completed
Tree (1)Type of Project : Reforestation
Location : Nattum, Mayoyao, IFUGAO
Name of People's Org'n : Nattum Irrigators Association
Name of PO/IPO Pres. : Pedro T. Ogasna
Project Cost : 1,160,000.00
Total Area : 50 Has.
Date Started : August 20,2012
Date Completion(Revised): December 2015
No. of refo sites : 1
Area Planted/% Planted : 50 Has./100%
Total Amount Released : 896,512.50
Balance Amount : 263,487.50
REMARKS : Activities conducted

(2)Type of Project : Agroforestry
Name of People's Org'n : Nattum Irrigators Association
Location : Nattum, Mayoyao, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 14.00 Has.
Total Cost : 448,000.00
Date Started : October 2014
Date Completion(Revised): October 2015
Agro Plots : 31
Area Planted(Ha.) : 14 Has.
Area Planted(%) : 100%
Species Planted : Coffee and Manggo
Total Amt. Released : 397,415.47
Balance Amount : 50,584.53
REMARKS : Activities completed
Tree (1)Type of Project : Reforestation
Location : Magulon, Mayoyao, IFUGAO
Name of People's Org'n : Maga-Magulon Farmers Association
Name of PO/IPO Pres. : Benjie A. Chilagan
Project Cost : 1,160,000.00
Total Area : 50 Has.
Date Started : August 20,2012
Date Completion(Revised): March 2016
No. of refo sites : 2
Area Planted/% Planted : 50 Has./100%
Total Amount Released : 749,025.00
Balance Amount : 410,975.00
REMARKS : Last pass maintenance not yet conducted

(2)Type of Project : Agroforestry
Name of People's Org'n : Highland Farmers & Handicraft Association
Location : Magulon, Mayoyao, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 20 Has.
Total Cost : 640,000.00
Date Started : Sept. 28, 2014
Date Completion(Revised): October 2015
Agro Plots : 33
Area Planted(Ha.) : 20 Has.
Area Planted(%) : 100%
Species Planted : Coffee
Total Amt. Released : 644,181.82
Balance Amount : -4,181.82
REMARKS : Activities completed
Tree (1)Type of Project : Assisted Natural Regeneration(ANR)
Location : Piwong, Hingyon, IFUGAO
Name of People's Org'n : Piwong Farmers Organization
Name of PO/IPO Pres. : Jerry H. Tundagui
Project Cost : 384,600.00
Total Area : 30 Has.
Date Started : August 20,2012
Date Completion(Revised): September 2015
No. of refo sites : 2
Area Planted/% Planted : 30 Has./100%
Total Amount Released : 346,139.90
Balance Amount : 38,460.10
REMARKS : Activities completed

(2)Type of Project : Agroforestry
Name of People's Org'n : Piwong Farmers Organization
Location : Piwong, Hingyon, IFUGAO
Name of PO/IPO Pres. : Jerry H. Tundagui
Total Area : 9.06 Has.
Total Cost : 289,920.00
Date Started : October 2014
Date Completion(Revised): September 2015
Agro Plots : 31
Area Planted(Ha.) : 9.06 Has.
Area Planted(%) : 100%
Species Planted : Rambutan
Total Amt. Released : 260,928.00
Balance Amount : 289,920.00
REMARKS : Activities completed
Tree Type of Project : Reforestation
Location : Bangtinon, Hingyon, IFUGAO
Name of People's Org'n : Bangtinon Farmers Association
Name of PO/IPO Pres. : Joel A. Ampoc
Project Cost : 2,340,680.00
Total Area : 134(60 Refo/74 ANR-Expansion)Has.
Date Started : August 20, 2012/August 5, 2014(Expansion)
Date Completion(Revised): September 2015/June 2016(Expansion)
No. of refo sites : 3
Area Planted/% Planted : 134 Has./100%
Total Amount Released : 1,693,026.00
Balance Amount : 647,654.00
REMARKS : Activities completed/Last pass maintenance not yet conducted(Expansion Area)
FMR Proponent :MLGU
Province :IFUGAO
Municipality:TINOC
Barangay :AHIN
Name of Sub-Project:Improvement of DENGAW-SUYONG FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status:COMPLETED
CFA/Non-CFA:NON CFA
Quantity:0.44
Unit:KMS.
Total Project Cost:2,100,740.00
Fund Source:OFID
% Physical Accomplishment:100%
REMARKS:PHYSICALLY COMPLETED,100% PROJECT COUNTERPART RELEASED
FMR Proponent :MLGU
Province :IFUGAO
Municipality:TINOC
Barangay :LUHONG
Name of Sub-Project:Rehabilitation of GUMHANG-LUHONG FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status: COMPLETED
CFA/Non-CFA:CFA (75M)
Quantity:4.44
Unit:KMS.
Total Project Cost:6,842,250.00
Fund Source:IFAD
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED, 100% PROJECT COUNTERPART RELEASED
FMR Proponent :MLGU
Province :IFUGAO
Municipality:TINOC
Barangay :TUCUKAN
Name of Sub-Project:Improvement/Rehab. of MANHUYUHOY-TUCUKAN FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status:COMPLETED
CFA/Non-CFA:NON CFA
Quantity:4.0
Unit:KMS.
Total Project Cost:7,000,000.00
Fund Source:IFAD
% Physical Accomplishment:100%
REMARKS:PHYSICALLY COMPLETED
FMR Proponent :MLGU
Province :IFUGAO
Municipality:TINOC
Barangay :TUCUKAN
Name of Sub-Project:Improvement of MANHUYUHOY-GADAY FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status:COMPLETED
CFA/Non-CFA:NON CFA
Quantity:0.68
Unit:KMS.
Total Project Cost:4,000,000.00
Fund Source:OFID
% Physical Accomplishment:100%
REMARKS:PHYSICALLY COMPLETED,100% PROJECT COUNTERPART RELEASED
Home Proponent :MLGU
Province :IFUGAO
Municipality:TINOC
Barangay :AHIN
Name of Sub-Project:DENGAW, Ahin IP Hall
Sub-Project Type:COMMUNITY INFRASTRUCTURE
Implementation Status: COMPLETED
CFA/Non-CFA:NON CFA
Quantity:1
Unit:UNIT
Total Project Cost:600,000.00
Fund Source:OFID
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED
Home Proponent :MLGU
Province :IFUGAO
Municipality:TINOC
Barangay :DANGGO
Name of Sub-Project:DANGGO IP Hall
Sub-Project Type:COMMUNITY INFRASTRUCTURE
Implementation Status:ON-GOING
CFA/Non-CFA:NON CFA
Quantity:1
Unit:UNIT
Total Project Cost:600,000.00
Fund Source:OFID
% Physical Accomplishment : 50%
REMARKS: ON-GOING IMPLEMENTATION
Home Proponent :MLGU
Province :IFUGAO
Municipality:TINOC
Barangay :LUHONG
Name of Sub-Project:LUHONG IP Hall
Sub-Project Type:COMMUNITY INFRASTRUCTURE
Implementation Status: COMPLETED
CFA/Non-CFA:NON CFA
Quantity:1
Unit:UNIT
Total Project Cost:600,000.00
Fund Source:OFID
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED, 100% PROJECT COUNTERPART RELEASED
Home Proponent :MLGU
Province :IFUGAO
Municipality:TINOC
Barangay :TUCUKAN
Name of Sub-Project:TUKUCAN WAREHOUSE (IP Hall)
Sub-Project Type:COMMUNITY INFRASTRUCTURE
Implementation Status: COMPLETED
CFA/Non-CFA:NON CFA
Quantity:1
Unit:UNIT
Total Project Cost:600,000.00
Fund Source:OFID
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED

 

Tree (1)Type of Project : Reforestation
Location : Camandag, Asipulo, IFUGAO
Name of People's Org'n : Camandag Farmers Association
Name of PO/IPO Pres. : Jose L. Manawit
Project Cost : 812,000.00
Total Area : 35 Has.
Date Started : February 27,2012
Date Completion(Revised): December 2015
No. of refo sites : 3
Area Planted/% Planted : 35 Has./100%
Total Amount Released : 627,558.75
Balance Amount : 184,441.25
REMARKS : Activities completed

(2)Type of Project : Agroforestry
Name of People's Org'n : Camandag Farmers Association
Location : Camandag, Asipulo, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 15.00 Has.
Total Cost : 480,000.00
Date Started : October 2014
Date Completion(Revised): October 2015
Agro Plots : 34
Area Planted(Ha.) : 15 Has.
Area Planted(%) : 100%
Species Planted : Rambutan/Lanzones
Total Amt. Released : 392,945.66
Balance Amount : 87,054.34
REMARKS : Activities completed

 

 

 

 

 

 

 

Tree (1)Type of Project : Reforestation
Location : Chaya, Mayoyao, IFUGAO
Name of People's Org'n : Chaya-Mayoyao Irrigators Association, Incorporated
Name of PO/IPO Pres. : Jayson L. Maayon
Project Cost : 1,991,865.90
Total Area : 86(55 Refo/31 Expansion)Has.
Date Started : May 12,2011/March 2014(Expansion)
Date Completion(Revised): December 2014/March 2016(Expansion)
No. of refo sites : 2
Area Planted/% Planted : 86 Has./100%
Total Amount Released : 1,609,794.81
Balance Amount : 382,071.09
REMARKS : Activities completed/Last pass maintenance not yet conducted(Expansion)

(2)Type of Project : Agroforestry
Name of People's Org'n : Chaya-Mayoyao Irrigators Association, Inc.
Location : Chaya, Mayoyao, IFUGAO
Name of PO/IPO Pres. : -
Total Area : 6.77 Has.
Total Cost : 216,640.00
Date Started : October 2014
Date Completion(Revised): September 2015
Agro Plots : 37
Area Planted(Ha.) : 6.77 Has.
Area Planted(%) : 100%
Species Planted : Coffee
Total Amt. Released : 194,976.00
Balance Amount : 21,664.00
REMARKS : Activties completed
Tree (1)Type of Project : Reforestation
Location : Mompolia, Hingyon, IFUGAO
Name of People's Org'n : Mompolia Farmers Association
Name of PO/IPO Pres. : Pedro Dumaguing Sr.
Project Cost : 1,156,969.00
Total Area : 50 Has.
Date Started : May 16,2011
Date Completion(Revised): December 2014
No. of refo sites : 2
Area Planted/% Planted : 50 Has./100%
Total Amount Released : 1,041,272.10
Balance Amount : 115,696.90
REMARKS : For final validation

(2)Type of Project : Agroforestry
Name of People's Org'n : Mompolia Farmers Association
Location : Mompolia, Hingyon, IFUGAO
Name of PO/IPO Pres. : Pedro S. Dumaguing, Sr.
Total Area : 9.68 Has.
Total Cost : 309,760.00
Date Started : February 8,2013
Date Completion(Revised): February 2015
Agro Plots : 27
Area Planted(Ha.) : 9.68 Has.
Area Planted(%) : 100%
Species Planted : Coffee, Beetle nut
Total Amt. Released : 278,784.00
Balance Amount : 30,976.00
REMARKS : Activities completed
Drinking Water Proponent :MLGU
Province :IFUGAO
Municipality:HUNGDUAN
Barangay :BOKIAWAN
Name of Sub-Project:Rehab. of PUNHAGBAN-NUNBUHILING DWS
Sub-Project Type:DOMESTIC WATER SUPPLY
Implementation Status:COMPLETED
CFA/Non-CFA:NON CFA
Quantity:1.0/30
Unit:UNIT/HHs
Total Project Cost:452,901.86
Fund Source:OFID
% Physical Accomplishment:100%
REMARKS:PHYSICALLY COMPLETED
Tree (1)Type of Project : Reforestation
Location : Bokiawan, Hungduan, IFUGAO
Name of People's Org'n : Bokiawan Farmers Organization
Name of PO/IPO Pres. : Mateo O. Gano
Project Cost : 971,853.96
Total Area : 42 Has.
Date Started : May 16,2011
Date Completion(Revised): December 2014
No. of refo sites : 1
Area Planted/% Planted : 42 Has./100%
Total Amount Released : 874,668.59
Balance Amount : 97,185.37
REMARKS : Activities completed

(2)Type of Project : Agroforestry
Name of People's Org'n : Agayap Agriculture and Livelihood Association
Location : Bokiawan, Hungduan, IFUGAO
Name of PO/IPO Pres. : Elena Paddapad
Total Area : 8.59 Has.
Total Cost : 274,880.00
Date Started : March 1, 2013
Date Completion(Revised): March 2015
Agro Plots : 23
Area Planted(Ha.) : 8.59 Has.
Area Planted(%) : 100%
Species Planted : Nangka, Beetle nut
Total Amt. Released : 247,392.00
Balance Amount : 27,448.00
REMARKS : Activities completed
FMR Proponent :MLGU
Province :IFUGAO
Municipality:ASIPULO
Barangay :PULA
Name of Sub-Project:Improvement of DAKEL-DANUM FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status:COMPLETED
CFA/Non-CFA:CFA (50M)
Quantity:4.92
Unit:KMS.
Total Project Cost:10,000,000.00
Fund Source:OFID
% Physical Accomplishment:100%
REMARKS:PHYSICALLY COMPLETED,100% PROJECT COUNTERPART RELEASED
FMR (1)Proponent:MLGU
Province :IFUGAO
Municipality:HINGYON
Barangay :UBUAG-MOMPOLIA
Name of Sub-Project:Improvement of MOMPOLIA-UBUAG FMR
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status: COMPLETED
CFA/Non-CFA:CFA (50M)
Quantity:2.59
Unit:KMS.
Total Project Cost:8,154,862.16
Fund Source:OFID
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED,100% PROJECT COUNTERPART RELEASED

(2)Proponent:MLGU
Province :IFUGAO
Municipality:HINGYON
Barangay :UBUAG-MOMPOLIA
Name of Sub-Project:Improvement of MOMPOLIA-UBUAG FMR Ph2
Sub-Project Type:FARM TO MARKET ROAD
Implementation Status: COMPLETED
CFA/Non-CFA: NON-CFA
Quantity:1.35
Unit:KMS.
Total Project Cost: 3,700,000.00
Fund Source:IFAD
% Physical Accomplishment: 100%
REMARKS: PHYSICALLY COMPLETED